No email gate and no download. The answer is on the page, because a contractor who can see his own WIP line does not need to be sold one.
In short
What tools does Blackthorne Wicker give away?
A working WIP calculator. Put in the contract amount, what you have billed, what you have spent and what it will cost to finish, and it returns percent complete, earned revenue, over or under billing and profit at completion. Nothing is emailed and nothing is gated.
How to read it
Reading a WIP line
A WIP schedule is one line per job, and the line only tells the truth if the cost to complete is honest.
Percent complete is cost to date divided by total expected cost. Earned revenue is the contract multiplied by that percentage. If you have billed more than you have earned, you are overbilled, and that cash is borrowed from the rest of the job. If you have billed less, you are underbilled, and you have done work you have not been paid for.
Neither one is automatically bad. Both are dangerous when nobody is watching them.
NextAustin, Texas
Which job loses money right now?
You cannot see the profit on a job. You must calculate it.